Current report number 17/2024 of May 15, 2024
Management Board of VIGO Photonics S.A. ("Company", "Issuer") informs that today it has received information about the signing of an agreement by the National Center for Research and Development with the Company for co-financing the Issuer's project entitled: "HyperPIC
- Photonic integrated circuits for mid-infrared applications" (abbreviated as " Project”) under Priority II. An environment conducive to innovation Measure 2.10 IPCEI Recruitment FENG.02.10-IP.01-002/23, European Funds for a Modern Economy 2021-2027. The project will be implemented as part of the integrated European project IPCEI ME/CT (Important Projects of Common European Interest on Microelectronics and Communication Technologies).
- The Issuer informed about the decision of the European Commission approving the maximum ceiling of public aid in the project in current report No. 22/2023 of June 12, 2023, and about its inclusion on the list of entities recommended for co-financing in current report No. 13/2024 of February 23, 2024.
- The aim of the project is to develop and implement the technology of integrated photonic integrated circuits intended for mid-infrared detection, to build a complete production line of mid-infrared photonic integrated circuits and to create a complete supply chain for these systems. The project requires the development of new technologies, significant investment and operational expenditure, as well as expenditure on the commercialization of new products on a dynamic market.
- The total value of eligible costs in the project is PLN 853,117,563.35, and the maximum amount of public aid is PLN 440,535,480.00, which corresponds to the so-called financial gap in the project. Eligible costs in the project include expenditure on research and development work, expenditure on the construction of a new production line and operating costs after launching the new production line.
- The update of the value of eligible costs and subsidies expressed in PLN results from the fact that they are re-calculated from the values expressed in EUR listed in the decision of the European Commission (approving the maximum ceiling of public aid) at the exchange rate on the date of conclusion of the Agreement at the average exchange rate of foreign currencies - announced by the National Bank of Poland - applicable on the day the aid was granted. The project is planned to be implemented in 2023-2029 and consists of two phases:
– R&D phases (2023-2027). The value of eligible costs in the R&D phase is PLN 146,366,042.37
– FID (First Industrial Deployment) phase, i.e. the first industrial implementation (2024- 2029), including investments in a new production line and implementation of new products into production, including financing of part of the operating costs during implementation. The value of eligible costs in the FID phase is PLN 706,751,520.98.
After the end of the FID phase, it is planned to start serial production (after 2029), which does not include public funding for the project. The Company's Management Board anticipates that the eligible costs of the project, above the value of funding from public funds, will be covered from the Company's funds and equity, from debt financing and/or, in particular in the FID phase, from other sources, such as, among others, strategic project partnership and/or off- balance sheet financing in the project finance formula.